The Union Cabinet, chaired by Prime Minister Narendra Modi, has extended the Pradhan Mantri Gram Sadak Yojana-III (PMGSY-III), aimed at upgrading rural road connectivity, from March 2025 to March 2028, This extension focuses on enhancing connectivity for villages to essential services like schools, hospitals & markets..
Financial Revisions intiated because

- Total Outlay Increased to ₹83,977 crore , it was up from ₹80,250 crore
- The Central Government will contribute ₹54,848 crore, with states providing ₹29,129 crore
- Maintains the 60:40 for Centre:State ratio & 90:10 for North-Eastern/hilly regions…
Project time line extends
- in Plain Areas , Completion extended to March 2028
- in Hilly areas Road completion by March 2028, with bridges extended to March 2029
- Focus on upgrading “Through Routes” & “Major Rural Links” to improve access to essential amenities
Socio-Economic Impact

- Aims to enhance farm-to-market connectivity, boosting rural incomes
- Contributes to the Viksit Bharat 2047 mission by improving infrastructure, service access, and creating jobs
- This approval aligns with other government initiatives, including a 2% DA hike and the ₹12,980 crore Bharat Maritime Insurance Pool
For More Govt Scheme visit the Link and to know our Vision visit here
Join TEN Today
Follow us on Instagram, YouTube, X , telegram , Linkedin , Arattai a & Kubza for daily updates.
We are deeply aligned with our Tagline that is “Empowering Wisdom” , One verified story at a time.
I believe you love to Visit and Subscribe at given above Link for Better Version of Current affairs News at www.eminentnews.com /www.eminentnews.in , please join us to Learn, Leap and Lead in Life with mutual trust and coordination ..
Thank you !!!